Public Notices / Road Construction 

Current Road Construction Projects

2019 Asphalt Overlay Project

Project Locations: 

  • Winkler Road – Green-Randolph Rd north to Fancy Creek Rd
  • Crooked Creek Road – Barton Rd north to Green-Randolph Rd 
  • Kansas Avenue & Crooked Creek Rd – Union Rd west to US-24

Awarded to Shilling Construction Co., Inc. in the amount of $1,466,665.50. Project scheduled to begin in August 2019.

Fancy Creek Road Bridge Project No. F.5-5.9

Consultant - Bartlett & West. Project awarded to Ebert Construction, Wamego, KS, in the amount of $949,188.39.

Vinton School Road Culvert Replacement Project No. N.1-30.0

Consultant - Benesch. Project awarded to Ebert Construction, Wamego, KS, in the amount of $133,806.30. Construction scheduled to begin August 1, 2019.

Anderson Avenue Bridge Replacement Project No. N.7-23.6

Consultant - BG Consultants. Project awarded to Reece Construction Co. Inc., Salina, KS in the amount of $812,976.01. Project scheduled to begin October 7, 2019.

Stockdale Park Road Bridge Replacement Project No. L.9-17.7

Consultant - Schwab Eaton, P.A. Project awarded to Ebert Construction, Wamego, KS, in the amount of $805,644.57. Construction scheduled to begin May 6, 2019.

Future Construction Projects

Kitten Creek Road Culvert Replacement Project No. N.5-22.5

  • Consultant - Olsson Associates
  • Under design.

Peach Grove Road Culvert Replacement Project No. I.0-4.2

  • Consultant - SMH Consultants, P.A.
  • Field Check Plans reviewed by staff
  • Office Check Plans received and under review
  • Negotiating easement acquisitions